Projects / Sewerage Projects / Bhubaneswar Sewerage Projects

Orissa Water Supply & Sewerage Board (OWSSB), Bhubaneswar is implementing the Integrated Sewerage Project in Bhubaneswar City.
The objective of the project is to improve the Sewerage facility in Bhubaneswar City covering an estimated population of 22 lakhs (2041) over an area of 145 sq.km.
Bhubaneswar Sewerage System is divided into six sewerage districts for implementation of integrated sewerage system each district having its own and Sewer Network ,Sewerage Treatment Plant       and Sewage Pumping Stations.

Bhubaneswar sewerage system is segregated into 6 sewerage districts as Dist. -I , II, III, IV, V ,VI. The       sewerage system work is under progress in each district except Dist. V.

Capacity of STPs in Bhubaneswar

  • Dist. I – 56 MLD (Work under progress)
  • Dist. II- 28 MLD (Work under progress)
  • Dist. -III- 43.5 MLD (Work under progress)
  • Dist.- IV- 8 MLD (Work under progress)
  • Dist. VI- 48 MLD (Work under progress)

Agency: M/s Iron Triangle Limited & M/s Laxmi Construction (JV)

Commencement Date: 24th Aug 2017

Schedule Completion Date: 23rd August 2020

Construction Cost: Rs. 181.26 Cr

O&M Cost : Rs.15.23 Cr

Scope of Work

o Sewer Laying : 30.12 Km

o Pumping Stations: 5 Nos

o STP : 56 MLD

Agency: M/s Laxmi Construction infra Projects Pvt. Ltd.

Commencement Date: 29th November 2017

Schedule Completion Date: 28th November 2020

Construction Cost: Rs. 136.83 Cr

O&M Cost : Rs. 26.24 Cr

Scope of Work

o Sewer Laying : 41.22 Km

o Pumping Stations: 14 Nos

o STP : 28 MLD

Agency: M/s TATA Project Limited-SG Infratech Project Limited (JV)

Commencement Date: 9th August 2017

Schedule Completion Date: 8th August 2020

Construction Cost: Rs. 298.78 Cr

O&M Cost: Rs. 46.58 Cr

Scope of Work

o Sewer Laying : 106.05 Km

o Pumping Stations: 9 Nos

o STP : 43.5 MLD

Agency: M/s Laxmi Construction Infra Projects Pvt. Ltd.

Commencement Date: 27th February 2018

Schedule Completion Date: 26th February 2020

Construction Cost: Rs. 48.40Cr

O&M Cost : Rs. 9.73 Cr

Scope of Work

o Sewer Laying : 16.42 Km

o Pumping Stations: 5 Nos

o STP : 8 MLD

Agency: M/s IVRCL Ltd. M/s Va Tech Wabag

Commencement Date: 26.06.2013

Construction period: 8 (Eight) Years   and   O&M Period: 7 (Seven) Years

Construction Cost: Rs.696.84 Cr   and   O&M for 7 yrs: Rs. 55.99 Crs

Scope of Work

o Gravity Sewer : 253.86 Km

o Pumping Stations: 20 Nos. (Including MHPS)

o STP : 1 No 48 MLD STP at Rokat, Bhubaneswar