Bhubaneswar sewerage system is segregated into 6 sewerage districts as Dist. -I , II, III, IV, V ,VI. The sewerage system work is under progress in each district except Dist. V.
Capacity of STPs in Bhubaneswar
Agency: M/s Iron Triangle Limited & M/s Laxmi Construction (JV)
Commencement Date: 24th Aug 2017
Schedule Completion Date: 23rd August 2020
Construction Cost: Rs. 181.26 Cr
O&M Cost : Rs.15.23 Cr
o Sewer Laying : 30.12 Km
o Pumping Stations: 5 Nos
o STP : 56 MLD
Agency: M/s Laxmi Construction infra Projects Pvt. Ltd.
Commencement Date: 29th November 2017
Schedule Completion Date: 28th November 2020
Construction Cost: Rs. 136.83 Cr
O&M Cost : Rs. 26.24 Cr
o Sewer Laying : 41.22 Km
o Pumping Stations: 14 Nos
o STP : 28 MLD
Agency: M/s TATA Project Limited-SG Infratech Project Limited (JV)
Commencement Date: 9th August 2017
Schedule Completion Date: 8th August 2020
Construction Cost: Rs. 298.78 Cr
O&M Cost: Rs. 46.58 Cr
o Sewer Laying : 106.05 Km
o Pumping Stations: 9 Nos
o STP : 43.5 MLD
Agency: M/s Laxmi Construction Infra Projects Pvt. Ltd.
Commencement Date: 27th February 2018
Schedule Completion Date: 26th February 2020
Construction Cost: Rs. 48.40Cr
O&M Cost : Rs. 9.73 Cr
o Sewer Laying : 16.42 Km
o Pumping Stations: 5 Nos
o STP : 8 MLD
Agency: M/s IVRCL Ltd. M/s Va Tech Wabag
Commencement Date: 26.06.2013
Construction period: 8 (Eight) Years and O&M Period: 7 (Seven) Years
Construction Cost: Rs.696.84 Cr and O&M for 7 yrs: Rs. 55.99 Crs
o Gravity Sewer : 253.86 Km
o Pumping Stations: 20 Nos. (Including MHPS)
o STP : 1 No 48 MLD STP at Rokat, Bhubaneswar