Cuttack sewerage system is segregated into 2 sewerage districts as SD -I , II.
Capacity of STPs in Cuttack
Agency: M/s Larsen & Toubro Ltd. & M/s Va Tech Wabag
Commencement Date: Sewerage Network: 18.02.2013 & STPs and PSs Construction: 22.07.2013
Construction period: 8 (Eight) Years and O&M Period: 7 (Seven) Years
Schedule Date of Completion : Sewerage Network: 03.09.2020 STPs and PSs Construction: 30.06.2020
Construction Cost: Rs. 1058.82 Cr
O&M for 7 yrs: Rs. 76.19 Crs
o Gravity Sewer : 382 Km
o Pumping Stations: 36 Nos. (Including MHPS)
o STP : 2 Nos of STPs of 36 MLD and 16 MLD Capacity at CDA and Matagajapur in Cuttack respectively