Projects / Sewerage Projects / Cuttack Sewerage Projects

Cuttack sewerage system is segregated into 2 sewerage districts as SD -I , II.

Capacity of STPs in Cuttack

  • SD I – 36 MLD (Work under progress)
  • SD II- 16 MLD (Work under progress)

Agency: M/s Larsen & Toubro Ltd. & M/s Va Tech Wabag

Commencement Date: Sewerage Network: 18.02.2013 & STPs and PSs Construction: 22.07.2013

Construction period: 8 (Eight) Years and O&M Period: 7 (Seven) Years

Schedule Date of Completion : Sewerage Network: 03.09.2020 STPs and PSs Construction: 30.06.2020

Construction Cost: Rs. 1058.82 Cr

O&M for 7 yrs: Rs. 76.19 Crs

Scope of Work

o Gravity Sewer : 382 Km

o Pumping Stations: 36 Nos. (Including MHPS)

o STP : 2 Nos of STPs of 36 MLD and 16 MLD Capacity at CDA and Matagajapur in Cuttack respectively