Shri Naveen Patnaink
Hon'ble Chief Minister,Orissa

Projects / Septage Projects / Cuttack Septage Project

► Capacity:60 KLD
► Cost: INR 176Lakhs
► Year of commissioning:January 2020
► Technology: Solid-liquid separation+ Co-treatment
► Catering to population of 1,44,000
► Salient features:
  • The SeTP in Cuttack employs co-treatment for septage management. The solids present in the septage are separated in a settling-cum-thickener tank, which is then taken to the sludge drying bed for drying and disposal. The liquid part of the septage is treated in the STP located adjacent to the SeTP.
  • In a historic step, the Operation & Maintenance (O&M) of the SeTP is being handled by Bahucharamata Transgender Self Help Group (SHG).